Being on the 3rd floor, routing new mechanicals to accommodate the new fixture locations made was the primary challenge for this project.
Additional time was taken in this phase to ensure all fixtures were supplied and drained properly. However, this did not affect the overall estimated timeframe.
This project was designed by Rachel Henry of Sanctuary Designs. Rachel worked closely with the client and worked through the overall floor plan, material selections, tile pattern, color palettes & textures that make this space complete.
During the design phase, we worked with Rachel & the client to establish a realistic budget for the project, timeframe, start date and more. Once the designs were completed, selections were made we had all the information to present a formal proposal.
The customer is given access to Buildertrend, a platform where we manage all of our projects, providing the customer with daily updates for completed phases, submit change orders, secured payments & more
With the designs confirmed, selections made, budget set, time frame arranged & signed project proposal it was time to get started. With all material selections made, ordering was made easy. We ordered all the materials directly to our shop in preparation for the project start date and ensured all items were indeed correct and intact. Just one damaged item could have caused unnecessary lead time.
Demolition & Rough-in Mechanicals
Mechanicals continued & start of waterproofing
Drywall patch & start of subway wall tile. Laundry Linen Shelving was fabricated, finished & installed.
Wall tile continued, recessed niche tile & shower floor tile
Vanity is installed, Start of Herringbone Feature wall tile, floor tile, Countertop Template & Glass Template
Vanity, plumbing & electrical fixtures are installed & grouting tile
Countertop & Glass are installed, trim is installed, ceiling & walls are painted. The work site is thoroughly cleaned, a final walkthrough with the customer is performed & the project concludes.
A month later we scheduled a site visit for a final review, address any minor items the customer might have discovered & perform the project completing photos